|
July 10, 2000
For Immediate Release
Contact: Jim Kleissler, Allegheny Defense Project, (814) 223-4996
Jim Bensman, Heartwood, (618) 259-3642
Forest Protection Groups Appeal Federal Court Decision
Clarion, PA - On Thursday, June 29, only 24 hours
after receiving a Federal Court's decision denying their request
for a Temporary Restraining Order and Preliminary Injunction against
clearcut logging on the Allegheny National Forest, forest protection
advocates filed for an expedited appeal in the case.
On September 23, 1999, the U.S. Forest Service approved
the Shingle Mill Timber Sale on the Allegheny National Forest ending
a 6-month moratorium on logging activities. The moratorium was put
in place to protect the federally endangered Indiana bat (Myotis
sodalis), two endangered species of freshwater mussel, and the threatened
Bald eagle. The Indiana bat was only recently documented on the
Allegheny. The Northern riffleshell mussel is of special concern,
as one of the only two reproducing populations of the species resides
in the Allegheny River where it flows through the national forest.
The Allegheny Defense Project, a Clarion, Pennsylvania,
based non-profit, and Heartwood, Inc., a Bloomington, Indiana, based
non-profit filed their lawsuit in Federal Court in Pittsburgh on
September 29, 1999. They requested that a Temporary Restraining
Order be granted to prevent the U.S. Forest Service, managers of
the National Forest System, from proceeding with logging plans on
the Allegheny.
"There are nearly 9,000 acres of our national forest
at stake here," explained James Kleissler, Forest Watch Director
for the Allegheny Defense Project and a Plaintiff in the lawsuit.
"Most of that logging is clearcut logging where large areas of the
Allegheny National Forest and habitat for endangered species will
be destroyed. The endangered Indiana bats require large dead and
dying trees for roosting. These are the very trees that are being
targeted by the Forest Service for logging. Erosion and sedimentation
as a result of logging operations are a tremendous threat to endangered
freshwater mussels, which are very sensitive to these effects."
Federal Judge Donetta Ambrose took nearly nine months
to rule on the forest protection groups' request to stop logging.
"Normally, in other lawsuits we've filed, when we
ask for a Temporary Restraining Order against logging we get a decision
that same day," explained Jim Bensman, Forest Watch Director for
Heartwood. "Judge Ambrose took 9 months. In one case we filed we
were able to get a Judge to issue a Restraining Order the day we
asked for it even though he was on vacation. The whole point of
asking for a Temporary Restraining Order is because you need immediate
relief to stop the cutting while the case is heard."
In their motion requesting that their appeal be given
urgent consideration, Bill Luneburg, the volunteer attorney for
the environmental groups, writes: "The Plaintiffs patiently awaited
the Court's final decision. November, 1999 came and went and so
did the next eight months without issuance of a decision by the
District Court."
"It is entirely unusual for the District Court to
sit on a Temporary Restraining Order for so long," explained Luneburg.
The environmental groups blasted Judge Ambrose's decision
denying their request for a Temporary Restraining Order. They argue
that their primary legal arguments remain unaddressed by the Courts.
"Judge Ambrose's Opinion actually fails to address
our legal arguments," explained Kleissler. "We cannot understand
how she can take 9 months to make a decision that should have been
made in one day and then fail to address our legal arguments. We
are very disappointed with the handling of this case."
"You cannot go to the Court of Appeals until the District
Judge issues a ruling. Judge Ambrose's unreasonable delay in ruling
on our request stopped us from appealing to stop the irreparable
harm to the public and endangered species," says Bensman. "She did
not need to wait 9 months to ignore everything we said. She could
have denied our motion for a Temporary Restraining Order when we
filed it and allowed us to appeal. In the meantime, the Forest Service
has been out there clearcutting our national forest."
One of the groups' legal claims dealt with the U.S.
Forest Service's denial of citizen appeal rights that they say are
normally allowed in similar circumstances.
"She relied entirely on case-law related to a set
of federal appeal regulations that no longer exist," asserted Bensman.
"In 1993, Congress enacted the Appeals Reform Act and the U.S. Forest
Service subsequently adopted new appeal regulations. She relied
on cases that dealt with the outdated, non-existent appeal regulations
for defending the Forest Service's actions. She completely ignored
the new regulations. This is entirely inexcusable."
Other legal claims before the Judge argued that the
U.S. Forest Service failed to appropriately respond to issues raised
by the public.
"I don't think the Judge seriously considered our
legal arguments," stated Kleissler. "If she had she couldn't have
drawn such cursory conclusions. Her Opinion doesn't explain why
the Forest Service doesn't need to respond to certain issues raised
by the public. She merely summarily concludes that the Forest Service
is not required to respond to public comments, entirely ignoring
the federal regulations which state the Forest Service 'shall address
comments received from the public during the comment period…'"
According to the Allegheny Defense Project, the ruling
will affect logging on nearly 9,000 acres of the Allegheny National
Forest. Over 6,000 acres of that cutting will be in the form of
clearcutting where nearly all of the trees are removed from an area
of the forest. Only 221 acres of the 9,000 acres of cutting is in
the form of selective cutting, a less environmentally damaging practice
that removes only a small portion of trees from an area of forest.
Neither the U.S. Forest Service nor intervening parties
(which includes primarily timber companies) have objected to the
forest protection groups' request for expedited consideration. A
decision from the Federal District Court of Appeals on the environmental
groups' motion is expected within two to three weeks. The Plaintiffs
also have several major legal claims that remain in front of the
District Court in Pittsburgh.
##
|